Question: The is the point at which the risk becomes enough of a reality the Pi needs to begin the contingency. This is a judgement
The
is the point at which the risk becomes enough of a reality the Pi needs to begin
the contingency.
This is a judgement call meant to maximize the value of the predetermined contingency ba implementing it at the optimal time, in order to not waste time, money ond effort.
Determining when to start the contingency is the trickiest part of the project risk diar
Select one
Lis
a Risk Point
D Contingency Point
Management Point
d Starting Point
e Trigger Point