Question: The IT implementation project is bogging down and falling behind schedule. The department heads are complaining that the project cannot help them if it is

The IT implementation project is bogging down and falling behind schedule. The department heads are complaining that the project cannot help them if it is not implemented in a reasonable time frame. Your project manager is considering putting extra resources to work on activities along the critical path to accelerate the schedule. This is an example of what? Select one: a. Crashing b. Identifying critical dependencies c. Fast-tracking the project d. Rebaselining