Question: The items discussed in a ( n ) _ _ _ _ _ include reflections on whether project goals were met, whether the project was

The items discussed in a(n)_____ include reflections on whether project goals were met, whether the project was successful or not, causes of variances on the project, reasoning behind corrective actions chosen, use of different project management tools and techniques, and personal words of wisdom based on team members' experiences.
which is correct?
a.
final project report
b.
audit report
c.
lessons-learned report
d.
design document