Question: The key to all scheduling techniques is to Multiple Choice make sure to allow a 2 0 percent delay factor to account for contingencies. distinguish

The key to all scheduling techniques is to
Multiple Choice
make sure to allow a 20 percent delay factor to account for contingencies.
distinguish tasks that must be done sequentially from those that can be done concurrently.
assign responsibility for end results to the entire group rather than a single individual.
avoid scheduling tasks that can be done concurrently.
avoid tasks that must be done sequentially.