Question: The level schedules technique . . . Question 7 options: requires that schedules be met without variation. processes many small batches rather than one large

The level schedules technique ...
Question 7 options:
requires that schedules be met without variation.
processes many small batches rather than one large one.
is known as "jelly bean" scheduling.
is based on meeting one day's demand with that day's production.
All of the above are true regarding level scheduling.