Question: The list below has the only 4 paths in a project, along with their respective durations. ACGI 23 ADFI 21 BDGI 24 BEGI 20 What
The list below has the only 4 paths in a project, along with their respective durations.
ACGI 23
ADFI 21
BDGI 24
BEGI 20
What is the slack time of activity A?