Question: The logical , hierarchical and organized task list developed with the team is called: Requirements Schedule RASIC matrix Work Breakdown Structure
The logical hierarchical and organized task list developed with the team is called:
Requirements
Schedule
RASIC matrix
Work Breakdown Structure