Question: The longest path in a project network has a duration of 25 weeks. The variance of the longest path is 4 weeks. Required: Determine the

 The longest path in a project network has a duration of

The longest path in a project network has a duration of 25 weeks. The variance of the longest path is 4 weeks. Required: Determine the probability (in percent) of completing the project in 28 weeks