Question: The longest path through the network expected time is 81 days. What is the probability that the job will be complete on the 83 rd

The longest path through the network expected time is 81 days. What is the probability that the job will be complete on the 83rd day if path variance is 1.8?

90.3%

91.6%

92.2%

92.9%

93.2%