Question: The main difference between the project management (PM) and the construction management (CM) procurement delivery approaches is that the PM team generally takes responsability for
The main difference between the project management (PM) and the construction management (CM) procurement delivery approaches is that the PM team generally takes responsability for design coordination as well as supervision of those responsible for delivering the work packages. True or False