Question: The manufacturing process uses three machines: A,B, and C. Machine A takes one hour for the product to pass through. Machine B takes two hours

The manufacturing process uses three machines: A,B, and C. Machine A takes one hour for the product to pass through. Machine B takes two hours for the product to pass through. Machine C takes one hour for the product to pass through. Machine B is an example of: goal congruence a variance a bottleneck an accelerant