The Marina Pools, Inc. operate three departments; namely Department 1, 2, and 3. In Department 1, the
Question:
The Marina Pools, Inc. operate three departments; namely Department 1, 2, and 3. In Department 1, the whole process covers ten days;
in Department 2, twelve days; and in Department 3 twenty days. In December 1992, Department 1 transferred to Department 2, 30,000 units at a total costs of 45,000. In Department 2 and Department 3, conversion cost are applied evenly, while material application are as follows:
Department 2: One-fifth of the material requirement is added at the start of the process; one-half when the process is one-third completed; and the balance, when the process is three-fourths completed.
Department 3: One-half of the material requirement is added at the start of the process, one-tenth when the process is one-fifth completed; and the remainder when the process is six-eights completed
Data for Department 2 and 3 for December 1992, follows:
Department 2 Department 3
Units in process, December 1 1,200 2,000
Number of days worked 5 6
Transferred out 28,080 25,580
Units in process, December 31 3,120 4,500
Number of days worked 7 11
In process, December 1 2,981 5,110
Current costs (December):
Materials 14,712 4,122
Labor 8,820 2,745.50
Overhead 2,940 1,372.75
Requirements:
Prepare a cost production report for Department 2 and 3 for the month of December 1992 (Use FIFO and Weighted average method)