Question: The materials manager for a billiard ball maker must periodically place orders for resin, one of the raw materials used in producing billiard balls. She
The materials manager for a billiard ball maker must periodically place orders for resin, one of the raw materials used in producing billiard balls. She knows that manufacturing uses resin at a rate of 50 kilograms each day, and that it costs $.04 per day to hold a kilogram of resin in inventory. She also knows that the order costs for resin are $100 per order, and that the lead time for delivery is four (4) days. Without allowing for safety stock, what reorder point should be used to reorder resin?
Multiple Choice
-
0 kilograms remaining
-
50 kilograms remaining
-
200 kilograms remaining
-
400 kilograms remaining
-
500 kilograms remaining