Question: The maximum possible cycle time in a flow shop layout is determined by the: A. shortest task time B. average task time C. longest task
The maximum possible cycle time in a flow shop layout is determined by the:
| A. | shortest task time | |
| B. | average task time | |
| C. | longest task time | |
| D. | total task time |