The MaxwellCorporation is evaluating the following project. The CFO has determined that the appropriate risk-adjusted discount rate
Question:
The MaxwellCorporation is evaluating the following project. The CFO has determined that the appropriate risk-adjusted discount rate is 7%.
Year Cash Flow
0 -15,000,000
1 3,950,000
2 3,500,000
3 3,800,000
4 -1,000,000
5 3,500,000
6 3,000,000
7 -1,000,000
8 2,000,000
9 2,000,000
Please answer the questions and correct my answers.
1. Calculate the net present value for the project. (Round to 2 decimals)
NPV on excel = 197,454 (wrong)
2. Calculate the profitability index for the project. (Round to 3 decimals)
Formula- (NPV/Initial investment)/ Initial investment = 1.014 (unsure)
3. Calculate the payback period for the project. (Round to 3 decimals) =
4. Calculate the discounted payback period for the project. (Round to 3 decimals) = -4.06 wrong