Question: The mean time between failures for a certain production machine is 250 hrs and the mean time to repair is 6 hrs. The availability of

  1. The mean time between failures for a certain production machine is 250 hrs and the mean time to repair is 6 hrs. The availability of the machine is:

    A.

    0.973

    B.

    0.024

    C.

    1.024

    D.

    1.025

    E.

    0.976