Question: The milestone schedule in the project charter: a . is a summary - level schedule that identifies significant points or events in the project. b

The milestone schedule in the project charter:
a.
is a summary-level schedule that identifies significant points or events in the project.
b.
is a summary-level schedule that shows how major project tasks are sequenced.
c.
is a schedule that provides detailed data for when each project activity should begin.
d.
is a detailed schedule that shows the planned duration for every activity in the project