Question: The Monsanto supply chain team selects a linear forecasting model with b=6.9 and a=128. Calculate the linear forecasted demand for quarters 13 to 15 .
The Monsanto supply chain team selects a linear forecasting model with b=6.9 and a=128. Calculate the linear forecasted demand for quarters 13 to 15 . Then, given the actual demand for quarters 13 to 15 below, compare it with your forecasts. What is the mean absolute percentage error (MAPE)? Note: Only the MAPE answer should be entered below as a percentage (one place of decimal)