Question: The multiplication process used by MRP to determine lower - level requirements is called Multiple Choice exploding. pegging. time - phasing. projecting. netting.

The multiplication process used by MRP to determine lower-level requirements is called
Multiple Choice
exploding.
pegging.
time-phasing.
projecting.
netting.