Question: The network below represents a project being analyzed by the critical path method. Activity durations are J=10.5,K=8,L=6.5,M=3,N=5,O=7, and P=7.5 What is the length of the

The network below represents a project being analyzed by the critical path method. Activity durations are J=10.5,K=8,L=6.5,M=3,N=5,O=7, and P=7.5 What is the length of the critical path? KMNP =23.5 JLP=24.5 JMNO =25.5 JMNP =26 JLPO=31.5
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts