Question: The network diagram and task times for a project are shown below. A2 A1 A3 Task Duration (days) A1 A2 A3 A4 A5 835006
The network diagram and task times for a project are shown below. A2 A1 A3 Task Duration (days) A1 A2 A3 A4 A5 835006 A4 A5 Answer is complete but not entirely correct. What is the slack for activity A3? 6 > days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock