Question: The network diagram and task times for a project are shown below. A A A4 A5 A3 Duration (days) 9 Task A1 A2 A3 A4

The network diagram and task times for a project are shown below. A A A4 A5 A3 Duration (days) 9 Task A1 A2 A3 A4 8676 2 1 9 A5 What is the slack for activity A3? days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
