Question: The network diagram and task times for a project are shown below. A2 A A4 A Task A1 A2 A3 AG As Duration (days) 8

The network diagram and task times for a project
The network diagram and task times for a project are shown below. A2 A A4 A Task A1 A2 A3 AG As Duration (days) 8 3 5 8 0000 6 days What is the late start time for activity A3