Question: The network diagram and task times for a project are shown below. What is the late start time for activity A 3 ? Task Duration

The network diagram and task times for a project are shown below.

What is the late start time for activity A3?

Task Duration (days)
A1 4
A2 7
A3 4
A4 3
A5 1