Question: The network diagram below represents the stages and time frames ( in days ) that Mr Phelan needs to follow in order to achieve government

The network diagram below represents the stages and time frames (in days) that Mr Phelan needs to follow in order to achieve government approval in the REIPPP process for this next solar project.
3.1: Redraw this network diagram and then perform the forward and backward passes for this phase.
(16 marks)
3.2: Calculate and give the length of this approval process.
(1 mark)
3.3: Give the critical path for this process.
(6 marks)
3.4: Which activities have slack time?
(2 marks)