Question: The network diagram for a project has the following three paths Path Mean Duration Variance 1 55 5 2 47 7 3 54 10 4
The network diagram for a project has the following three paths
| Path | Mean Duration | Variance |
|---|---|---|
| 1 | 55 | 5 |
| 2 | 47 | 7 |
| 3 | 54 | 10 |
| 4 | 22 | 3 |

The network diagram for a project has the following three paths Path Mean Duration Variance 1 55 5 2 47 7 3 54 10 4 22 3 What is the likelihood that the project will complete in 60 time units or less? Select the nearest percentage. [Recommended time:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
