Question: The network given was the original schedule for project ABC. table [ [ Act , table [ [ No . of ] ,

The network given was the original schedule for project ABC.
\table[[Act,\table[[No. of],[Days],[worked]],\table[[Remaining],[Duration]]],[A,12,3],[B,4,0],[C,9,0],[D,0,7],[E,3,0],[F,7,0],[G,0,2],[H,0,3],[I,0,4],[J,0,5],[K,0,1],[L,0,2],[M,0,3],[N,1,0],[O,0,8]]
After 12 workdays the project status was described by the data in the Table. Update the CPM network to answer the following questions:
The LF for activity D is:
21
20
23
None of the above
18
19
22
24