Question: The next 3 questions are based on the image below. flow time.png Here is a hypothetical process flowchart depicting part of a loan application process.
The next questions are based on the image below.
flow time.png
Here is a hypothetical process flowchart depicting part of a loan application process. The processing times in minutes are listed below each activity. What is the process flow time in minutes
None of the given options
flow time.png
The flow time is minutes:
IncorrectQuestion
pts
What is the Critical Path?
Process and Separate, Activity B Loan Officer
Process and Separate, Activity A Activity C
Activity A Activity B Loan Officer
Process and Separate, Activity A Activity B Loan Officer
The Critical Path is the one labeled as F: Process and Separate, Activity A Activity B Loan Officer.
IncorrectQuestion
pts
If the Activity C is reduced in time by what will be the process time?
Since Activity C is not on the critical path, the flow time will not change minutes
IncorrectQuestion
pts
If Activity B is increased in time by what will be the process time?
Since Activity B is on the critical path, the flow time will increase by minutes, to minutes.
IncorrectQuestion
pts
A bottleneck is the
Fastest activity in a process
Fastest resource or resource pool in a process
Slowest activity in a process
Slowest resource or resource pool in a process
Question
pts
True or False. The Effective Capacity of the bottleneck becomes the effective capacity of the entire process.
True
False
Question
pts
The comparison among Throughput R Effective Capacity, and Theoretical Capacity is generally stated as
R Effective Capacity Theoretical Capacity
R Effective Capacity Theoretical Capacity
R Effective Capacity Theoretical Capacity
R Effective Capacity Theoretical Capacity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock