Question: The original PERT task duration formula weights the most likely time method heavier than PMI's newer and simpler Three Point Estimation method. Suppose a task

The original PERT task duration formula weights the most likely time method heavier than PMI's newer and simpler Three Point Estimation method. Suppose a task has an optimistic time of 3 days, a mostly likely time of 24 days, and a pessimistic time of 36 days. If Project Manager A uses the older PERT formula, and Project Manager B uses the newer Three Point Estimation method, which of the following would be true?
Question 11 options:
Project Manager B's estimate for the expected duration of that task would be 1.5 days shorter than Project Manager A's estimate
Project Manager A's estimate for the expected duration of that task would be 0.5 days shorter than Project Manager B's estimate
Project Manager B's estimate for the expected duration of that task would be 0.5 days shorter than Project Manager A's estimate
Project Manager A's estimate for the expected duration of that task would be 1.5 days shorter than Project Manager B's estimate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!