Question: The original PERT task duration formula weights the most likely time method heavier than PMI's newer and simpler Three Point Estimation method. Suppose a task
The original PERT task duration formula weights the most likely time method heavier than PMI's newer and simpler Three Point Estimation method. Suppose a task has an optimistic time of days, a mostly likely time of days, and a pessimistic time of days. If Project Manager A uses the older PERT formula, and Project Manager B uses the newer Three Point Estimation method, which of the following would be true?
Question options:
Project Manager Bs estimate for the expected duration of that task would be days shorter than Project Manager As estimate
Project Manager As estimate for the expected duration of that task would be days shorter than Project Manager Bs estimate
Project Manager Bs estimate for the expected duration of that task would be days shorter than Project Manager As estimate
Project Manager As estimate for the expected duration of that task would be days shorter than Project Manager Bs estimate
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock