Question: The partially completed inventory record for the rotor sub assembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.

The partially completed inventory record for the rotor sub assembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.

a. Complete the last three rows of the record for an FOQ of

150

units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)

Item: Rotor sub assembly

Lot Size:

FOQ equals=150

units

Lead Time: 2 weeks

Week

1

2

3

4

5

6

7

8

Gross

requirements

55

10

55

40

80

80

80

80

Scheduled

receipts

150

Projected on-hand

inventory

25

Planned

receipts

Enter your answer in the edit fields and then click Check Answer.

The partially completed inventory record for the driveshaft sub assembly in the table below shows gross requirements, scheduled receipts, lead time, and currenton-hand inventory.

b. Complete the last three rows of the record for an FOQ of

55

units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)

Item: Driveshaft sub assembly

Lot Size:

FOQ equals=55

units

Lead Time: 3 weeks

Week

1

2

3

4

5

6

7

8

Gross

requirements

40

25

15

20

35

35

50

50

Scheduled

receipts

80

Projected on-hand

inventory

10

Planned

receipts

Enter your answer in the edit fields and then click Check Answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!