Question: The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory 1

The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory

1 2 3 4 5 6 7 8
Gross requirements 55 20 45 30 85 85 85 85
Scheduled Receipts 160
Projected on hand inventory 20
Planned Receipts
Planned Order Releases

a. Complete the last three rows of the record for an FOQ of 160 units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)

b. Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)

c. Complete the last three rows of the record by using the POQ lot-sizing rule, with P=2. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!