Question: The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory 1
The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
| Gross requirements | 55 | 20 | 45 | 30 | 85 | 85 | 85 | 85 | |
| Scheduled Receipts | 160 | ||||||||
| Projected on hand inventory | 20 | ||||||||
| Planned Receipts | |||||||||
| Planned Order Releases |
a. Complete the last three rows of the record for an FOQ of 160 units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
b. Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
c. Complete the last three rows of the record by using the POQ lot-sizing rule, with P=2. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts