Question: The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory. a.
The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
a. Complete the last three rows of the record for an FOQ of
160
units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
| Item: Rotor subassembly | Lot Size: FOQ=160 units | ||||||||
| Lead Time: 2 weeks | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
| Gross requirements | 75 | 15 | 55 | 30 | 85 | 85 | 85 | 85 | |
| Scheduled receipts | 160 | ||||||||
| Projected on-hand inventory | 15 | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Planned receipts | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | |
| Planned order releases | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
b. Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
| Item: Rotor subassembly | Lot Size: L4L | ||||||||
| Lead Time: 2 weeks | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
| Gross requirements | 75 | 15 | 55 | 30 | 85 | 85 | 85 | 85 | |
| Scheduled receipts | 160 | ||||||||
| Projected on-hand inventory | 15 | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Planned receipts | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | |
| Planned order releases | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
c. Complete the last three rows of the record by using the POQ lot-sizing rule, with
P=2.
(Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
| Item: Rotor subassembly | Lot Size: POQ (P=2) | ||||||||
| Lead Time: 2 weeks | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
| Gross requirements | 75 | 15 | 55 | 30 | 85 | 85 | 85 | 85 | |
| Scheduled receipts | 160 | ||||||||
| Projected on-hand inventory | 15 | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |
| Planned receipts | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | |
| Planned order releases | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here | enter your response here |