Question: The partially completed inventory record for the tabletop subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on - hand

The partially completed inventory record for the tabletop subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
Item: Lot Size:
M405long dashX
Description: Tabletop subassembly
Lead Time: 2 weeks
Week
12345678910
Gross 9595704595
requirements
Scheduled 115
receipts
Projected on-hand
3535
inventory
Planned
receipts
Planned order
releases
Complete the last three rows of the record for an FOQ of 115
units.