Question: The PERT activity durations are shown on the spreadsheet, use this information to calculate the 95 % probability duration. For example, Optimistic : 16 Most
The PERT activity durations are shown on the spreadsheet, use this information to calculate the 95% probability duration.
For example, Optimistic : 16 Most Likely: 21 Pessimistic: 28 PERT Estimate: 21.333333
Please explain how to calculate the 95% probability duration. Thank you very much.