Question: The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 2900 units, the actual direct labor cost
The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 2900 units, the actual direct labor cost was $58125 for 3750 direct labor hours worked, the total direct labor variance is
|
| $7125 unfavorable. |
|
| $2900 unfavorable. |
|
| $7125 favorable. |
|
| $3375 unfavorable. |