Question: The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1700 units, the actual direct labor cost

The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1700 units, the actual direct labor cost was $40000 for 2000 direct labor hours worked, the total direct labor variance is $11000 unfavorable. O$1700 unfavorable. $5500 unfavorable. $11000 favorable. The standard rate of pay is $23 per direct labor hour. If the actual direct labor payroll was $99440 for 4400 direct labor hours worked, the direct labor price variance is $2200 unfavorable. $1760 favorable. $2200 favorable. $1760 unfavorable