Question: The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1500 units, the actual direct labor cost
The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1500 units, the actual direct labor cost was $43200 for 2700 direct labor hours worked, the total direct labor variance is
|
| $1125 unfavorable. |
|
| $1800 favorable. |
|
| $1800 unfavorable. |
|
| $1500 unfavorable. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts