Question: The plan sheets for a pavement project include the installation of Guard Rail, Type B from station 1 2 4 3 + 0 0
The plan sheets for a pavement project include the installation of "Guard Rail, Type B
from station to Rd the unit for guard rail is Ft linear feet The Schedule
of Items for contract bidding purposes shows a quantity of of "Guard Rail, Type B
Assume the quantity shown on the plan sheet is the correct quantity and will be the actual
quantity installed and paid for.
Contractor bid prices and the Average Item Price range for "Guard Rail, Type B are as
follows:
a point What is the error in quantity in Show your calculation.
b pointsComplete the table below. Show your calculation for the bid adjustment
for each contractor.
c point Is the bid materially unbalanced? Why or why not?
YES or NO
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock