Question: The planned value for a project is US$17,800, the earned value is US$19,450, and the actual cost is US$21,870. Based on this information, calculate the

  1. The planned value for a project is US$17,800, the earned value is US$19,450, and the actual cost is US$21,870. Based on this information, calculate the cost performance index and the schedule performance index. What do these indices tell you about the status of the project in terms of cost and schedule?

2. The budget at completion of this project was estimated at US$20,000, and the original estimated time to complete was thirteen months. Use the information from the previous question to compute the estimated cost at completion and the projected time to complete. Is the project on budget and schedule?

Hint: The projected time to complete can be calculated by dividing the original estimated time to complete by the schedule performance index (SPI). (Projected time to complete = Original Estimated Time /SPI)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!