Question: The planned value for your project is $ 2 , 0 0 0 per week, and you are told that S V = - $

The planned value for your project is $2,000 per week, and you are told that SV=-$2,000. How would you interpret this?
A
You have $2,000 worth of work left to do.
B
You are over budget.
C
You have completed $2,000 worth of work.
D
You are behind schedule.