Question: The planning / control cycle has two control steps. What are they? Group of answer choices compare results and then correct deviations / improve the

The planning/control cycle has two control steps. What are they?
Group of answer choices
compare results and then correct deviations/improve the plan
research planning and then correct deviations/improve the plan
compare previous plans and then evaluate plans
make the plan and then carry out the plan
research planning and then receive feedback