Question: The PMBOK Guide 7 e describes eight project performance domains, groups of critical, related, and overlapping activities that are needed on all projects. In which
The PMBOK Guide e describes eight project performance domains, groups of critical, related, and overlapping activities that are needed on all projects. In which performance domain would the desired outcomes include: a reliable understanding of project status, actionable data for decision making, actions to keep performance on track, and achieving targets?