Question: The potential for projected cash flow errors to result in incorrect NPV estimates is called _____ risk. Multiple Choice Scenario. Projection. Monte Carlo. Accounting. Forecasting.
The potential for projected cash flow errors to result in incorrect NPV estimates is called _____ risk.
Multiple Choice
-
Scenario.
-
Projection.
-
Monte Carlo.
-
Accounting.
-
Forecasting.