Question: The predetermined overhead rate for Sheffield Corp. is $ 4 , comprised of a variable overhead rate of $ 2 and a fixed rate of

The predetermined overhead rate for Sheffield Corp. is $4, comprised of a variable overhead rate of $2 and a fixed rate of $2. The amount of budgeted overhead costs at normal capacity of $120000 was divided by normal capacity of 30000 direct labor hours, to arrive at the predetermined overhead rate of $4. Actual overhead for June was $9700 variable and $12000 fixed, and standard hours allowed for the product produced in June was 3700 hours. The total overhead variance is
$6900F.
$6900U.
$4600U.
$4600F.