Question: The primary purpose for a change management process is to: A. Record changes made to systems and infrastructure B. Review and approve proposed changes to

The primary purpose for a change management process is to:

A. Record changes made to systems and infrastructure

B. Review and approve proposed changes to systems and infrastructure

C. Review and approve changes to a project schedule

D. Review and approve changes to application source code