Question: The priority - sequencing rule for job shop scheduling that does not require knowledge of job due date is Part 2 A . critical ratio.

The priority-sequencing rule for job shop scheduling that does not require knowledge of job due date is
Part 2
A.
critical ratio.
B.
earliest due date.
C.
slack per remaining operations.
D.
shortest processing time.