Question: The problem with defining success as on time, within cost, and at the desired quality or performance level is that this is an internal definition

The problem with defining success as on time, within cost, and at the desired quality or performance level is that this is an internal definition of success only. Bad things can happen on projects when the contractor, customer, and various stakeholders are all focusing on different definitions of project success.