Question: The process flow in a distribution center will be diagramed on the board. Consider the following capacity statistics for each of the functions in the

The process flow in a distribution center will be diagramed on the board. Consider the following capacity statistics for each of the functions in the system: 1. Determine the total capacity of each function. What is the capacity of the entire system (i.e. of the DC), in orders/day? 2. Which function is the bottleneck? 3. What capacity should the functions that are upstream of the bottleneck run at? Why? 4. From your answer in Q3, what will be the utilization of each function? 5. How does the introduction of variability affect your answer to Question 3? 6. How can the capacity of the DC be increased? What will determine the new capacity after the change