Question: The process improvement manager has developed a new machine to cut material for running shoes. The material cannot be more than + - 0 .

The process improvement manager has developed a new machine to cut material for running shoes. The material cannot be more than +-0.02 of an inch from the required thickness of .455 inches. When you took samples (15 samples with 10 observations in each sample) of material cut from the new machine, you calculated the following data: (note: use 3 decimal places for calculations)
X-double bar =0.460,R-bar =0.15
a) What is the upper control limit (blank 1), and what is the lower control limit (blank
for the x-bar chart on this new machine? (use 3 decimal places)
b) what are the upper (blank 3) and lower (blank 4) control limits for the R chart on this new machine? (use 3 decimal places)
c) Given the UCL and LCL in part (a), do you believe the Cpk for the process is 1,>1, or 1?(please put one of the following answers (blank 5): 1,>1, or 1
Blank # 1
A
Blank # 2
Blank # 3
Blank # 4
Blank # 5
 The process improvement manager has developed a new machine to cut

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!