Question: The process of converting a general or outline plan for a project into a time-based graphical representation given information (inputs) on available resources and constraints,
The process of converting a general or outline plan for a project into a time-based graphical representation given information (inputs) on available resources and constraints, is known as: Question 43 options: Executing Scheduling Sequencing Planning